CIP Monthly Status Report – November 2018

Regional Wastewater Facility Headworks
In November, the City advanced one project through the Project Delivery Model stage gate process: the Headworks Project completed Interim Stage Gate 4.2- Revisit Budget and Schedule.

The Cogeneration Facility Project design-builder set four 3.1-megawatt engine generators on vibration isolators incorporated into a massive concrete slab completed last month. A 330-ton crane was required to set each of the engine generators on its base. The entire effort was completed in one day.

The Plant Instrument Air System Upgrade Project completed a 28-day commissioning test and achieved Beneficial Use. The new system provides compressed air with sufficient redundancy to all critical instruments in the Secondary Blower and Nitrification buildings.

The Digester and Thickener Facilities Upgrade Project continued with concrete work for the digester roofs, digester ring beam foundations, and sludge screening building walls.

The City accepted the Headworks Critical Improvements Project and filed the Notice of Completion and Acceptance with the County on November 8, 2018.